| One of our finish carpenters is setting nails on some upstairs window trim. |
| Another carpenter is cutting a piece of the base molding on the main floor. |
| Upstairs in the new Master Bedroom, the trim has been installed, the doors have been hung, and the walls have been painted. |
| Oak floors (the real old time stuff) will be installed in over 80% of the project. The remaining floors are ceramic tile, and sheet goods. |
| The oak floors are down, the walls are painted, and the ceiling fan is swinging in the master bedroom. |
| The finish has been applied to the floors. This project is really coming along now. Kitchen cabinets, built-ins, and electrical and plumbing fixtures are all that remains. |
| The oak Kitchen Cabinets have arrived and are being installed. |
| The ceramic tile in the mudd room is being set in the mud. |
| The cabinets have been set. It is now time to measure and order the granite countertops. |
| In addition to the Oak Kitchen Cabinets, there is also custom built-ins being fabricated in our own cabinet shop for the dining room. Here a finisher is spraying clear lacquer over the painted exterior, and natural oak interior. "A unique finish". |